Starting Monday, April 3rd, TriMet will perform annual maintenance on MAX transformers. Train stations and platforms will be without power from approximately 9 a.m. to 1 p.m. This outage will affect power to the ticket vending machines and TransitTracker. The outage will not affect the signal system.
Maintenance schedule:
Monday, April 3rd - Washington St. in Hillsboro
Tuesday, April 4th - PGE Park
Wednesday, April 5th - Beaverton Transit Center
Thursday, April 6th - Fair Complex/Hillsboro Airport