A Better Red extends MAX Red Line west to serve 10 more stations and improves schedule reliability for the entire MAX system.
— Drag to scroll —
Crews are working in the existing trackway, and building a new walkway and break facility for MAX operators.
Because much of the construction takes place in the trackway, certain activities are being performed at night, when there is little train traffic.
About one-third of the Park & Ride lot is closed for construction staging.
Updated Feb. 15: A temporary fence will remain along an area of the western portion of Veterans Memorial until crews are able to return and replant vegetation.
Crews are building a new track crossing, Red Line station platform, multi-use path and two new bridges:
Because construction is near highways and MAX tracks, some work takes place at night, when there is less traffic and fewer trains. Bridge construction also includes daytime pile driving and some detours for people walking and rolling.
Two public areas are closed for construction staging:
Updated Jan. 11:
I-205 north between approximately mile marker 21 to mile marker 22.
Crews are working along the MAX trackway adjacent to Gateway Green and Gateway Transit Center. The night work includes drilling, vacuum equipment, concrete pumping, rail cutting and welding.
A temporary asphalt detour path near the south entrance of Gateway Green will remain in place through construction in 2024.
Reduction of TriMet customer parking on the first floor of the garage.
Vehicle traffic reduced to one lane on Providence Medical Clinic Street. Please access the parking garage via NE Multnomah Street.
The south end of the park is closed for construction through late 2024.
TriMet’s contractor, Stacy & Witbeck, will be assisting in the reconstruction of hills and paths for the bike track near the work zone.
Crews are constructing a new station platform at PDX and new track adjacent to the existing track, along with a new multi-use path between the MAX station and NE 82nd Avenue.
Construction along Air Cargo Rd is being performed in multiple phases. Crews are repositioning the roadway. During this week, the following work is to be done:
Please note: With the A Better Project at more than 50% completion, rail components are now being delivered to the work site. As a result, there will be a higher frequency of trucks moving along Air Cargo Rd.
Email betterred@trimet.org or call 503-962-2150. For construction emergencies, call 503-962-2222.
Thank you for your patience during construction!